- Biodiversity and Ecosystem Resilience
- 19 November 2025
Background
- Biodiversity and Ecosystem Resilience
- 19 November 2025
Assessment Outcome
The following table sets out SEPA’s planned activity for year 2024/2025 and what was delivered. The planned activity and current status represent the numbers of barriers SEPA planned to have at each stage in April 2025 and the actual numbers at that stage. The planned activity figures are derived from the revised implementation plan received in 2024 with additionally identified barriers.
Throughout the implementation plan period, a significant number of additional barriers have been identified by SEPA. In 2023/24, SEPA identified an extra 104 barriers, and in 2024/25 an additional 26 barriers were found to exist. The total number of barriers included in the plan as of April 2025 is 374, which represents an increase of over 50% to those barriers originally identified as requiring licensing or removal.
| Stage |
Planned activity |
Current status (April 2025) |
| Stage 0 no action |
137 |
134 |
| Stage 1 screening |
0 |
93 |
| Stage 2 licensing and design |
146 |
117 |
| Stage 3 build |
34 |
4 |
| Stage 4 completed |
31 |
26 |
| TOTAL |
348 |
374 |
SEPA has advised ESS that a further 14 barriers had been identified between April 2025 and June 2025. Activity in respect of these barriers will be included in the April 2026 update.
- Biodiversity and Ecosystem Resilience
- 19 November 2025
Conclusion
From the information supplied it appears that SEPA is continuing to progress the programme, whilst continuing to integrate newly identified barriers into it. Despite good progress, delivery is behind the plan at most stages.
It is noted that according to the original programme, Stage 1 screenings should have been completed by April 2025. However, the data supplied by SEPA indicates 93 screenings are ongoing. This reflects the additional numbers of barriers identified after the programme commenced.
ESS notes the significant gap in the number of barriers planned to be at the build phase (Stage 3) and the number reported by SEPA to be at this stage. This may restrict SEPA’s ability to achieve the planned number of barriers due to be completed (stage 4) by April 2026.
SEPA planned for 31 barrier projects to be completed (Stage 4) by April 2025. 26 barriers have been completed.
ESS will seek an update on SEPA’s progress against the programme again in April 2026 and will report in due course.